Due to the persistence of winter weather (snow and cold temperatures), the Kansas Department of Transportation has issued a suspension of construction work (winter shutdown) on 41st Street between Smoky Hill Drive and Hall Street.
Work will resume once favorable weather has returned and the frozen ground has thawed. Once work resumes, the contractor will have approximately two months of work remaining to complete the project.
During the winter shutdown, the contractor will continue to maintain temporary surfaces and traffic control devices.
This is part of the continuing project to reconstruct 41st Street from the U.S. 183 Bypass to Hall Street.
For more information, call (785) 628-7350.