By BECKY KISER
Hays Post
Reconstruction of 13th Street between Main and Milner is scheduled to start Monday, May 11.
13th Street will be closed from Milner to Pine Street.
Traffic will be detoured to 8th Street, according to Assistant Public Works Director John Braun.
“Since there will be displaced parking and more traffic in alleys and side roads, motorists should use caution and be sure not to park in a way that would block traffic,” Braun advised.
“Construction involves replacement of all the pavement, including the sidewalk, curb and gutter and parking area. No on-street parking will be allowed in the construction zone.
“There’s been some misinformation out there, and we want to correct that. On-street parking will be restored after reconstruction is complete,” he emphasized.
The project also includes driveways, reconstructing the intersections, replacing storm sewer inlets, pipe and structures, all new water service, and installing brick-lined crosswalks at all intersections.
It is expected to be completed by Nov. 1.
The contract was awarded to APAC-Kansas, Inc. with the low bid of $2,067,710.