City of Hays
The reconstruction of 13th Street from Main to Milner continues.
13th Street remains closed from Pine to just west of Milner, and traffic is restricted to one-way east bound from Main to Oak.
The intersection of 13th and Allen is expected to be open to traffic by the end of this week on Friday, Oct. 2. Paving work will be done at the Allen and Pine Street intersections, from Allen to Pine, and Oak to Main north of the street center line. Next week, starting Monday, Oct. 5, 13th Street between Pine and Oak will be closed as well.

The City appreciates the public’s patience and understanding during the course of this project. If there are any questions, contact the Public Works Department at (785) 628-7350 or the contractor, APAC, at (785) 625-3459.